ARTICLE 13 TERMINATION OR SUSPENSION <br />§ 13.1 Termination or Suspension Prior to Execution of the Design -Build Amendment <br />§ 13.1.1 If the Owner fails to make payments to the Design -Builder for Work prior to execution of the Design -Build <br />Amendment in accordance with this Agreement, such failure shall be considered substantial nonperformance and <br />cause for termination or, at the Design -Builder's option, cause for suspension of performance of services under this <br />Agreement. If the Design -Builder elects to suspend the Work, the Design -Builder shall give seven days' written <br />notice to the Owner before suspending the Work. In the event of a suspension of the Work Me Design -Builder shall <br />have no liability to the Owner for delay or damage caused by the suspension of the Work. B`b ore resuming the <br />Work, the Design -Builder shall be paid all sums due prior to suspension and any expenses furred in the <br />interruption and resumption of the Design -Builder's Work. The Design -Builder's compensat on: for. and time to <br />complete, the remaining Work shall be equitably adjusted. <br />§ 13.1.2 If the Owner suspends the Project, the Design -Builder shall be compensated for the Work performed prior to <br />notice of such suspension. When the Project is resumed, the Design -Builder shall be compeated for expenses <br />incurred in the interruption and resumption of the Design -Builder's Work. The Design -Builder's compensation for, <br />and time to complete, the remaining Work shall be equitably adjusted. <br />§ 13.1.3 If the Owner suspends the Project for more than 90 cumulative days for reasons other than the fault of the <br />Design -Builder, the Design -Builder may terminate this Agreement by giving not less than seven :days' written <br />notice. <br />§ 13.1.4 Either party may terminate this Agreement upon not less than seven days' written ndt�ie� s�� the other <br />party fail substantially to perform in accordance with the terms of this Agreement through no fault of the party <br />initiating the termination. <br />§ 13.1.5 The Owner may terminate this Agreement upon not less than seven days' written notice to th e Design - <br />Builder for the Owner's convenience and without cause. <br />§ 13.1.6 In the event of termination not the fault of the Design -Builder, the Design -Builder shah be compensated for <br />Work performed prior to termination, together with Reimbursable Expenses then due and any*ether: expenses <br />directly attributable to termination for which the Design -Builder is not otherwise compensato event shall the <br />Design -Builder's compensation under this Section 13.1.6 be greater than the compensation set forth, in Section 2.1. <br />§ 13.2 Termination or Suspension Following Execution of the Design -Build Amendment <br />§ 13.2.1 Termination by the Design -Builder <br />§ 13.2.1.1 The Design -Builder may terminate the Contract if the Work is stopped for a period Qf 3 0 c©rzsecutive days <br />through no act or fault of the Design -Builder, the Architect, a Consultant, or a Contractor, or then^ merits or <br />employees, or any other persons or entities performing portions of the Work under direct or indirect ,Contract with <br />the Design -Builder, for any of the following reasons: <br />.1 Issuance of an order of a court or other public authority having jurisdiction that' "es all Work to be <br />stopped, t <br />.2 An act of government, such as a declaration of national emergency that requires all work to be <br />stopped; <br />.3 Because the Owner has not issued a Certificate for Payment and has not notified the Design -Builder of <br />the reason for withholding certification as provided in Section 9.5.1, or becaus'Nr er has not <br />made payment on a Certificate for Payment within the time stated in the Design -Build Documents; or <br />.4 The Owner has failed to furnish to the Design -Builder promptly, upon the Desigrlder's request, <br />reasonable evidence as required by Section 7.2.7. =h <br />§ 13.2.1.2 The Design -Builder may terminate the Contract if, through no act or fault of the Desl;Lign-Bonder, the <br />Architect, a Consultant, a Contractor, or their agents or employees or any other persons or entities performing <br />portions of the Work under direct or indirect contract with the Design -Builder, repeated suspensions, delays or <br />interruptions of the entire Work by the Owner as described in Section 13.2.3 constitute in the aggreg t' more than <br />100 percent of the total number of days scheduled for completion, or 120 days in any 365-day.period; whichever is <br />less. <br />AIA Document A1411 - 2014. Copyright © 2004 and 2014 by The American Institute of Architects. All rights reserved. WARNING: This AIAO <br />Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA9 Document, <br />or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the 2 8 <br />law. This draft was produced by AIA software at 13:59:58 ET on 04/09/2020 under Order No. 3456073873 which expires on 04/04/2021, and is <br />not for resale. <br />User Notes: <br />(3B9ADA54) <br />