ARTICLE 5 <br />_~ _ PROGRESS PAYMENTS <br />5.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for Payment issued by the <br />Architect, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and <br />elsewhere in the Contract Documents. <br />5.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month, or as <br />follows: <br />5.3 Provided an Aption for Payment is received by the Architect not later than the _ <br />day of a month, the Owner shall make payment to the Contractor not later than <br />the 30th day of the following month. If an Application for Payment is received by the <br />Architect after the application date fixed above, payment shall be made by the Owner not later than (Q <br />days after the Architect receives the Application for Payment. <br />5.4 Each Application for Payment shall be based upon the schedule of values submitted by the Contractor in accordance wi[h <br />the Contact Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work <br />and be prepared in such form and supported by such darn to substantiate its accuracy as the Architect may require. This schedule, <br />unless objected to by the Architect, shall be used as a basis for reviewing the Contractor's Applications for Payment. <br />5.5 Applications for Payment shall indicate the percentage of completion of each portion of the Work as of the end of the period <br />covered by the Application for Payment. <br />,9.. 5.6 Subject to the provisions of the Contract Documents, the amount of each progress payment shall be computed as follows: <br />~'~= <br />5.6.1. Take that portion of the Contract Sum properly allocable to completed Work as determined by multiplying the percentage <br />completion of each portion of the Work by the share of the total Contract Sum allocated to that portion of the Work in the schedule <br />of values, less retainage of eight percent <br />( g %). Pending final determination of cost to the Owner of changes in the Work, amounts not in the dispute maybe <br />included as provided in Subparagraph 7.3.7 of the General Conditions even though the Contract Sum has not yet been adjusted <br />by Change Order; <br />5.6.2 Add that portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the <br />site for subsequent incorporation in the completed construction (or, if approved in advance by the Owner, suitably stored off the <br />site at a location agreed upon in writing), less retainage of eight percent <br />percent ( 8 %); not applicable <br />5.6.3 Subtract the aggregate of previous payments made by the Owner; and <br />5.6.4 Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate for Payment as provided in Para- <br />graph 9.5 of the General Conditions. <br />5.7 The progress payment amount determined in accordance with Paragraph 5.6 shall be further modified under the following <br />circumstances: <br />5.7.1 Add, upon Substantial Completion of the Work, a sum sufficient to increase the total payments to <br />One hundred 'percent ( 100 %) of the Contract <br />Sum, less such amounts as the Architect shall determine for incomplete Work and unsettled claims; and <br />5.7.2 Add, if fmal completion of the Work is thereafter materially delayed through no fault of the Contractor, any additional <br />amounts payable in accordance with Subparagraph 9.10.3 of the General Conditions. <br />5.6 Reduction or limitation of retainage, if any, shall be as follows: Not applicable <br />(Ij it is intended, prior to Substantial Completion of the entire Work, to reduce or limit the retainage resulting jrom the percentages inserted in Subpard- <br />graphs 5.6. / and 5. G._' above, and this is not explained elsembere in the Contract Documents, insert here provisions jot such reduction or limitation.) <br />AIA DOCUMENT A101 OWNER-CONTRACTOR AGREEMENT TWELFi'H EDITION • AlA° • ©1987 A1O1-1957 4 <br />THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVENUE, N.W., WASHINGTON, D.G. 20006 <br />WARNING: Unlicensed photocopying violates U.S. copyright laws and is subject to legal proseeuUon. <br />