Init. <br />[ X] Not later than One hundred eighty( 180 ) calendar days from the date of commencement of the Work. <br />[ ] By the following date: <br />§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are <br />to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial <br />Completion of such portions by the following dates: <br />Portion of Work Substantial Completion Date <br />§ 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if <br />any, shall be assessed as set forth in Section 4.5. <br />ARTICLE 4 CONTRACT SUM <br />§ 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor's performance of the <br />Contract. The Contract Sum shall be Eight Hundred Sixty-eight Thousand Two Hundred Thirty-six Dollars and <br />Seventy-five Cents ($ 868,236.75 ), subject to additions and deductions as provided in the Contract Documents. <br />§ 4.2 Alternates <br />§ 4.2.1 Alternates, if any, included in the Contract Sum: <br />Item Price <br />ALT.1 Replace 4' Fence $10,200.00 <br />ALT. 2 Furnish and Install Drinking $18,000.00 <br />fountain./ waterline <br />§ 4.2.2 Subject to the conditions noted below, the following alternates may be accepted by the Owner following <br />execution of this Agreement. Upon acceptance, the Owner shall issue a Modification to this Agreement. <br />(Insert below each alternate and the conditions that must be met for the Owner to accept the alternate.) <br />Item <br />NA <br />§ 4.3 Allowances, if any, included in the Contract Sum: <br />(Identi each allowance.) <br />Item <br />NA <br />Price <br />Price <br />Conditions for Acceptance <br />§ 4.4 Unit prices, if any: <br />(Idents the item and state the unit price and quantity limitations, if any, to which the unit price will be applicable) <br />Item <br />NA <br />Units and Limitations Price per Unit ($0.00) <br />§ 4.5 Liquidated damages, if any: <br />(Insert terms and conditions for liquidated damages, if any.) <br />Not applicable <br />§ 4.6 Other: <br />(Insert provisions for bonus or other incentives, if any, that might result in a change to the Contract Sum.) <br />NA <br />AIA Document A10`11 — 2017. Copyright ®1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 ana 2U1 toy i ne <br />American Institute of Architects. All rights reserved. WARNING: This AIAO Document is protected by U.S. Copyright Law and International Treaties. <br />Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be <br />prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 09:43:01 ET on 02/27/2020 under Order <br />No.7558759643 which expires on 02/19/2021, and is not for resale. (1164067640) <br />User Notes: <br />