§4.3 Additional Services may be provided after execution of this Agreement,without invalidating the Agreement.
<br /> Except for services required due to the fault of the Architect,any Additional Services provided in accordance with this
<br /> Section 4.3 shall entitle the Architect to compensation pursuant to Section 11.3 and an appropriate adjustment in the
<br /> Architect's schedule.
<br /> §4.3.1 Upon recognizing the need to perform the following Additional Services,the Architect shall notify the Owner
<br /> with reasonable promptness and explain the facts and circumstances giving rise to the need.The Architect shall not
<br /> proceed to provide the following services until the Architect receives the Owner's written authorization:
<br /> .1 Services necessitated by a change in the Initial information,previous instructions or approvals given by
<br /> the Owner,or a material change in the Project including,but not limited to,size,quality,complexity,
<br /> the Owner's schedule or budget for Cost of the Work,or procurement or delivery method;
<br /> .2 Services necessitated by the Owner's request for extensive environmentally responsible design
<br /> alternatives,such as unique system designs,in-depth material research,energy modeling,or LEED/
<br /> certification;
<br /> .3 Changing or editing previously prepared Instruments of Service necessitated by the enactment or
<br /> revision of codes,laws or regulations or official interpretations;
<br /> .4 Services necessitated by decisions of the Owner not rendered in a timely manner or any other failure of
<br /> performance on the part of the Owner or the Owner's consultants or contractors;
<br /> .5 Preparing digital data for transmission to the Owner's consultants and contractors,or to other Owner
<br /> authorized recipients;
<br /> .6 Preparation of design and documentation for alternate bid or proposal requests proposed by the Owner;
<br /> .7 Preparation for,and attendance at,a public presentation,meeting or hearing;
<br /> .8 Preparation for,and attendance at a dispute resolution proceeding or legal proceeding,except where the
<br /> Architect is party thereto;
<br /> .9 Evaluation of the qualifications of bidders or persons providing proposals;
<br /> .10 Consultation concerning replacement of Work resulting from fie or other cause during construction;or
<br /> .11 Assistance to the Initial Decision Maker,if other than the Architect.
<br /> §4.3.2 To avoid delay in the Construction Phase,the Architect shall provide the following Additional Services,notify
<br /> the Owner with reasonable promptness,and explain the facts and circumstances giving rise to the need.If the Owner
<br /> subsequently determines that all or parts of those services are not required,the Owner shall give prompt written notice
<br /> to the Architect,and the Owner shall have no further obligation to compensate the Architect for those services:
<br /> .1 Reviewing a Contractor's submittal out of sequence from the submittal schedule agreed to by the
<br /> Architect;
<br /> .2 Responding to the Contractor's requests for information that are not prepared in accordance with the
<br /> Contract Documents or where such information is available to the Contractor from a careful study and
<br /> comparison of the Contract Documents,field conditions,other Owner-provided information,
<br /> Contractor-prepared coordination drawings,or prior Project correspondence or documentation;
<br /> .3 Preparing Change Orders and Construction Change Directives that require evaluation of Contractor's
<br /> proposals and supporting data,or the preparation or revision of instruments of Service;
<br /> .4 Evaluating an extensive number of Claims as the Initial Decision Maker;
<br /> .5 Evaluating substitutions proposed by the Owner or Contractor and making subsequent revisions to
<br /> Instruments of Service resulting therefrom;or
<br /> .6 To the extent the Architect's Basic Services are affected,providing Construction Phase Services 60
<br /> days after(I)the date of Substantial Completion of the Work or(2)the anticipated date of Substantial
<br /> Completion identified in Initial Information,whichever is earlier.
<br /> §4.3.3 The Architect shall provide Construction Phase Services exceeding the limits set forth below as Additional
<br /> Services.When the limits below are reached,the Architect shall notify the Owner:
<br /> .1 ( )reviews of each Shop Drawing,Product Data item,sample and similar submittal
<br /> of the Contractor
<br /> .2 ( )visits to the site by the Architect over the duration of the Project during construction
<br /> .3 ( )inspections for any portion of the Work to determine whether such portion of the
<br /> Work is substantially complete in accordance with the requirements of the Contract Documents
<br /> .4 ( )inspections for any portion of the Work to determine final completion
<br /> §4.3.4 . . . . • _ . .• • • - -, . - •
<br /> AIA Document 81017°—2007(formerly 8151 TM—1997).Copyright 61974,1978,1987,1997 and 2007 by The American Institute of Architects.All rights
<br /> /nit.
<br /> reserved.WARNING:This AIA Document is protected by U.S.Copyright Law and International Treaties.Unauthorized reproduction or distribution of 10
<br /> this AIA"Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to the maximum extent possible under
<br /> the law.This document was created on 06/12/2013 11:07:04 under the terms of AIA Documents-on-Demandlu order no. 2008611102 ,and is not for
<br /> resale.This document is licensed by the American Institute of Architects for one-time use only,and may not be reproduced prior to its completion.
<br />
|